First major slab pour complete

10 Jun 2016

MILESTONE ALERT!

We achieved our very first milestone on the weekend, with the completion of the first major concrete pour for the slab.

A total of 50 cubic metres of concrete was delivered by ten trucks, taking two hours to complete by a team of 12 site workers.

Our builders, Brookfield Multiplex are working hard as preparations are well underway for the next concrete pour this week.

FUN FACT: Did you know that 50 cubic metres would be equal to 700 household wheel barrows?